Work Planning

Structure Ranking Context

Structures are primarily ranked to inform field-assessment planning. Higher-ranked structures contribute greater potential toward habitat connectivity restoration and are therefore typically higher priorities for field assessment. They also represent key knowledge gaps with potential to significantly affect model results. Estimates of current connectivity status could improve considerably, for instance, if many high-ranking structures are passable or do not have habitat upstream. Habitat accumulation curves support decision making around how many and which structures should be assessed, by showing which structures may only minimally affect connectivity. High-ranked structures with minimal habitat upstream may be located low on these curves, because they must be addressed before benefits can be achieved by addressing lower-ranked barriers with more upstream habitat.

If confirmed as barriers, high-ranking structures are also often priorities for further field assessments to confirm upstream habitat before decisions are made about where fish passage should be rehabilitated.

Once field assessments are completed, management decisions are made for each assessed structure. An assessed structure may be excluded from the model if it is passable or there is no habitat upstream, or it may be listed as a priority barrier for fish-passage rehabilitation. Alternatively, some structures confirmed as barriers may be considered “non-actionable” because the amount and quality of habitat upstream may be low and the costs of rehabilitation may be high relative to those limited potential benefits.

Model ranks provide only limited information on the relative value of rehabilitation among priority barriers. Ranks convey only the relative amount of habitat upstream and do not represent other factors relevant to restoration prioritization, such as habitat quality, cost, social priorities, or logistical constraints and opportunities. Deciding which priority barriers to address first is a social decision-making process that is only partially informed by model outputs. Model outputs also provide broader context about how many structures exist in the system, how many have been identified as priority barriers, and how much habitat is upstream of each relative to others.

Workplan

Implementation plan for 2026-2027 to close knowledge gaps and advance barrier rehabilitation to improve connectivity for Westslope Cutthroat Trout in Qukin ?amak?is. Steps to incorporate field data, update models, and revise this WCRP are also included.

Action

Lead

Support

Timeline

Hold Planning Team meeting to review 2024 field results and determine next steps for barriers identified; and review permanently altered by mining outputs

CWF

Qukin ?amak?is Planning Team

Spring/ summer 2026

Update model based on Planning Team feedback

CWF

Qukin ?amak?is Planning Team

Fall 2026

Update WCRP with updated model outputs

CWF

Winter 2026-2027